Introduction

The river Günz is located in the southern part of Bavaria, Germany. It is about 55 km long and flows into the river Danube near the city Günzburg. The catchment area of the river Günz is 710 km². The Günz is fed by the confluence of the “Eastern Günz” and the “Western Günz” near the small city Lauben. The Test Case consists of a row of 5 consecutive hydropower plants, which are located on the Günz.

The hydrology of the Günz is characterized by peak flows in winter due to snow melting and some peak flows in the summer after heavy rain events. The catchment area of the river Günz is 710 km² The mean interannual discharge of the river Günz is estimated at 7.8 m³/s. The river is classified with a moderate ecological status.

MAP

Günz hydropower plant

The Test Case Günz comprises 5 consecutive hydropower plants. Four of them are run-of-river hydropower plants and one, the HPP Oberegg, has a diverted reach. Each of the 5 HPPs is equipped with one Kaplan-turbine, with installed capacities of 350 kW at Waldstetten, 450 kW at Höselhurst and Wattenweiler, 600 kW at Ellzee and 1100 kW at Oberegg. The annual output is between 1.8 – 3.7 millions kWh . The height drop ranges from 3.9 to 8.3 m at the different HPPs.

Layout
The HPPs Höselhurst, Wattenweiler, Ellzee and Waldstetten are run-of-river HPPs, the HPP Oberegg is a diversion hydropower plant (Ausleitungskraftwerk). In the upstream areas of the HPPs there are reservoirs. In the downstream areas the river Günz is still free flowing until the head of the next reservoir. There is a fish bypass channel at every HPP. At the run-of river HPPs they are built as a classical conventional pond system. At Oberegg the fish passage facility for upstream fish migration is integrated into the diverted reach, which is called “Alte Günz”.

Layout of the 5 HPPs of the Günz Test Case

Location of the 5 HPPs on the river Günz that are part of the Test Case

Characteristics
Country Germany
River Günz
Operator BEW
Capacity 350 - 1100 kW
HPPs 5
Inter-annual discharge 7.8 m³/s
1 Kaplan turbine at every HPP

The Operator: LEW Wasserkraft GmbH (LEW)
The LEW runs and maintains 36 HPPs at the rivers Danube, Günz, Lech and Iller and is thereby one of the leading HPP operator in Bavaria, Germany. The company produces over 1 billion kWh energy out of regenerative hydropower per year. Read more.

Challenges at the Test Case

Pressures on the water body's ecosystem
The main pressures on the water body are hydrology, agricultural use of pesticides, effluents from a nearby water treatment plant, and to some extent the spill over from storm water overflow. Previously, continuity was classified as a high pressure, but this was counteracted through the building of fishways in 2014. The pressures are mainly caused of morphological issues which are results of the HPP. There is a lack of important habitats like juvenile habitats, spawning habitats and the reophilic interstitial. The LEW is working on this problems with a restauration program.

Fish population
The river is dominated by reophilic fish species. The main species are white fish species like nase (Chondrostoma nasus), barbel (Barbus barbus), roach (Rutilus rutilus) and chub (Squalius cevalus). Furthermore, there are many small fish species like bleak (Alburnus alburnus), Bitterling (Rhodeus amarus) and gudgeon (Gobio gobio). Due to the anthropogenic river changes there are also many stagnopil species like pike (Esox lucius) and tench (Tinca tinca).

Upstream migration
There is a fish bypass channel for upstream migration at every HPP. The bypass channel at HPP Deisenhausen has a flow of 500 l/s and is 500 m long. All other fish bypass channels have a flow of 300 l/s and a length of 130 – 180 m. All fish bypass channels are built as a nature like pond system. The first 10 m of every fish bypass channel is built as a technical vertical slot pass to ensure a more or less consistent water flow. In every fish bypass channel there is furthermore a fish counting pool to register all (upward) migrating fish. This research study is done by Thomas Lechner (IBF Umwelt).

E-flow
The Test Case HPPs at the Günz are run-of river and diversion HPPs. The mean flow runs over the basin Oberegg, there is no hydropeaking. The old river called “Alte Günz” is used as a flood channel. The e-flow is 500 l/s at all time, which is the natural minimum water flow. This is the e-flow the authorities specified.

Pressures
Hydrology high
Morphology moderate
Pesticides significant
Water treatment plant effluents medium
Fish migration
Over 30 fish species
Fish bypass channels at ever HPP
Research objectives and tasks

This section of the Günz is strongly morphologic downgraded and channelized. The morphologic improvement of the Günz itself is difficult because of the closeness to the settlements and no available areas. Therefore, compensation habitats especially as spawning habitats and habitat for reophile fish species are being investigated to upgrade the ecology of strongly channelized rivers. Based on the findings, compensation habitats in the fish passes will be build.

Research tasks
The research tasks and field studies conducted at the HPPs on the river Günz are:

  • Potential scenario modelling
  • Construction. management and monitoring of spawning habitats in fishway
  • Numerical Simulation

Main FIThydro partners involved in the research at the Günz HPP

Research topics FIThydro partners
Status and quality of existing habitat structures BEW
Situation in the bypass reach, sediment composition and fish migration paths TUM
Optimization of habitat in bypass reach BEW
Research objectives
Compensation habitats
Spawning habitats
Update and results

Compensation habitat structures, especially as spawning habitat for reophile target fish-species such as nase and barbell, have been built in the fish-bypass channels and monitored for use. In spring 2018, a total of 42 t of washed gravel with a grain size of 16/32 mm was placed in selected pools of 3 of the 5 fishways. The fishways were then checked daily to document spawning and extract samples of substrate. The presence of fish fauna was monitored in all 5 fishways through electro-fishing.Already 4 days after the gravel placement in the fishway pools, successful spawning of nase could be documented in all three pools with fresh gravel in the fishway of the HPP Wattenweiler. Here, on about 50% of the fresh gravel stones at least one or several glued on nase eggs were found. On some of the previously existing coarse substrate in the fishway at the HPP Ellzee nase eggs were also found. However, these were only present in shadowed areas of the short technical part of the fishway under a bridge before the upstream exit.

Measurements in the fishway

Measurements in the fishway

Habitat creation through placement of gravel in the fishway

Habitat creation through placement of gravel in the fishway

picture rights: Areal pictures © Olav König; Hydropower plant in winter, detail of nature like fishway © Nicole Kalinowski, IBF Umwelt; Location map © LEW; Measurement in fishway © Mathias Schlagenhauser, TUM; Habitat creation © IBF, Umwelt